Skip to content

Michael Jordan Collision – 12

Michael Jordan Collision Center Sink Hole from Eddie Gontram on Vimeo.

A surprise, some more red tape, and a lot of progress this week at Michael Jordan Collision Center in Durham, NC.

The surprise was the sudden appearance of a sink hole in the parking lot.  Following installation of the oil-sand separator, and its subsequent tie-in to the existing sanitary sewer line under the parking lot, the trench as backfilled with washed stone and ready to be poured back.  However, the next day, it was discovered that 1 to 1-1/2 tons of stone disappeared into a 6″ diameter hole in the trench bottom that had opened up sometime during the night. We investigated with camera work, and once weather permitted, excavated the area.  We found that many years ago, the area had been backfilled with large rock.  Over the years, the fines that had filled the void between the rocks had washed away by ground water.  The void left behind easily swallowed the gravel once the weight of it overwhelmed the bottom of the new trench.  Once excavated, the pipe was repaired and the hole was backfilled with washed stone.  We pour it back this Saturday.

The red tape is related to the local jurisdiction’s time-consuming review of the new fire line and sprinkler permit.  This separate permit review has taken almost 5 months and has become critical path as far as the schedule is concerned.  The fire line permit was finally turned loose late in the week, but the sprinkler permit seems to be still in process.

Finally, lots of progress took place inside and outside of the building. The paint booths were almost complete.  Masonry walls for the new detail bays were completed.  Liner wall panels were installed inside the shop area.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.

Michael Jordan Collision – 11

It’s been a busy week at the Michael Jordan Collision Center in Durham, NC.

Michael Jordan Collision 2016-04-01 from Eddie Gontram on Vimeo.

Metal stud framing is now complete on the interior, and electrical wall rough-in is also nearing completion.  Plumbing rough-in finished earlier this week.

On the exterior, the new oil-sand separator tank (2,000-gallon concrete vault) was installed under the front parking lot.  Given the amount of rock encountered in other areas, we were relieved this installation went fairly smoothly.

A new sidewalk and steps was formed and poured to connect the Upper Level with the main entrance at the Lower Level.

Finally, the paint booths arrived and are about 50% complete.  They should be finished by the end of next week when the prep decks arrive.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.

NCAA Pool Complete!

GANCAAgif-2016Ten Penny Construction sponsors an annual NCAA Bracket Challenge with Gontram Architecture, and it is now complete!  Congratulations to all of the winners, and to the ultimate loser!

To see the final results, click HERE.

Since 1998, Gontram Architecture has hosted its NCAA Pool for the Men’s Division I tournament.  As in years past, there is NO entry fee, but lots of great prizes to be won! There’s even a nice trophy for the biggest loser.

New for 2016:  Jim Valvano’s words in his 1993 ESPY speech, “Don’t Give Up . . . Don’t Ever Give Up!”, have motivated millions of people to battle cancer and find a cure.  His dream of curing cancer is still not realized, but is closer because of his inspiration.  This year, for every Pool entry received, Gontram Architecture will donate $1 to The V Foundation for Cancer Research.  Participants also have to opportunity to give towards our “team” HERE, but it is not mandatory to play in our Pool.  We just wanted to give back to the organization founded by one of the most memorable personalities of this special Tournament.

If you want to contribute to the Gontram Architecture NCAA Pool fundraiser team for the V Foundation:  click HERE.

Michael Jordan Collision – 10

 

Michael Jordan Collision Center Timelapse 2016-04-01 from Eddie Gontram on Vimeo.

Two months to go at the Michael Jordan Collision Center project in Durham, NC.

The interior concrete work is now complete, allowing metal stud framing for the customer and office portion of the project to begin.  The 30-foot high stud walls were the first to be installed.

New high windows along the south side of the building were framed and trimmed out.

The wash bays on the Upper Level were poured, allowing for the masonry wing walls to be installed in a week or so.

The front entrance canopy and ADA ramp were poured.

LED high bay lighting has begun in the Lower Level.

Next week, more exciting work continues as the paint booths are delivered and installed, and the 2,000-gallon oil-sand separator will be installed below the front parking lot. Structural steel for the new canopy entrance area is also due early next week.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.

Michael Jordan Collision – 09

Another busy week has flown by at the Michael Jordan Collision Center project in Durham, NC.  Concrete has been placed for the walls at the front entrance area.  The remaining interior slab tie-ins were poured, and the vehicle ramp was just poured today.

The under-slab plumbing rough-in work at the Upper Level wash bays was also completed and ready for inspections and concrete next week.

Framing for the new storefront windows is also complete.

Next week, more exciting work continues as the final concrete pours for the entrance will be performed by mid-week, and the 2,000-gallon oil-sand separator will be installed below the front parking lot.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.

Michael Jordan Collision – 08

During the past week, a lot of concrete has been poured at the Michael Jordan Collision Center project in Durham, NC.  Concrete has been placed for both walls and floors.  Walls were formed and poured for the exterior front entry area and the interior vehicle access ramp.

Floors were poured where the plumbing trench drains had been recently installed.

The final under-slab plumbing rough-in work was also completed and ready for concrete tie-in next week.

New insulation facing continues to be installed on the Lower Level.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.

Michael Jordan Collision Center – 07

Michael Jordan Collision Timelapse Video 2016-03-11 from Eddie Gontram on Vimeo.

Another week gone by, a few more surprises, but a LOT of progress at the Michael Jordan Collision Center project in Durham, NC.

MJC_Front_Entry_Rebar

Front entry foundation work underway. New interior vehicle ramp work beyond.

Turning this medical records warehouse into a new body shop requires installing a ramp to allow vehicles from the front parking lot to drive into the building (currently at loading dock height).  Rather than taking up room in the parking lot for a large ramp, we saved those precious parking spots and are currently installing the ramp INSIDE the building.  That contributes to the demolished look of the overhead door openings.

MJC_Underground_Utilities

Discovered underground utilities.

Also, we have to get customers into the building at the office area.  So, we have a new “front porch” feature.  The foundation work for that area is currently underway.  More surprises:  drain piping and unsuitable soils mixed in with some bedrock has made for an interesting week.  Engineers were consulted, and we barely skipped a beat.

MJC_Pit_Decking_Embeds

Ventilation pit decking & embeds

Inside the building, the ventilation pits received embedded steel and pan decking and should be poured in a day or two.

Prime paint wrapped up on the Upper Level of the building.

Two new overhead doors were installed on the rear of the building.

MJC_OHD_install

New overhead door opening.

Michael Jordan Collision Center – 06

MJC_Pit_Footing_Rebar

Rebar in place for pit footings

Instead of tearing things up (demolition), positive “build back” construction activity occurred this week at the Michael Jordan Collision Center in Durham, NC.

MJC_trench_drain_set

Final sections of trench drain set in place

Trench drains are now 100% complete and set, ready for backfill and pouring.

The ventilation pits under the new paint booths were excavated (after getting some very hard rock out of our way).  Footings were poured for the pit walls, then the walls were formed, inspected, and today they were poured.  Column protection was also formed.

New overhead door openings in the building have been framed and are ready for door installation.

MJC_rear_drive_rough_grade

Rear service area getting to grade

The rear driveway was rough graded and the rear service area has begun to take shape.

All of the rock and excess fill from the interior of the building and rear access drive has now been hauled off, so more positive construction will proceed next week!

MJC_column_wrap_form

Formwork in place for column protection

Michael Jordan Collision Center – 05

Michael Jordan Collision 2016-02-26 from Eddie Gontram on Vimeo.

MJC_Rock1

Some rock has been removed from the ventilation pit excavation. The rock breaker receives some repair work.

With concrete cutting and removal complete, excavation for trench drains and paint booth ventilation pits commenced this week at the Michael Jordan Collision Center in Durham, NC.  It went fairly smoothly until the ventilation pits were dug.  In some spots, rock was found.  As these ventilation pits have very specific depth requirements, the rock must go!

MJC_Trench

Trench drain is installed and ready for inspection.

Next week, once the rock is removed, construction really amps up a notch as we can button up the slab and start building from the slab up.

More exploratory rock excavation will also take place out back, behind the building.

MJC_Duct_Tape

Duct tape can fix anything, I guess!

Michael Jordan Collision Center – 04

Michael Jordan Collision 2016-02-17 from Eddie Gontram on Vimeo.

Concrete cutting and removal was underway this week at the Michael Jordan Collision Center in Durham, NC.  Slabs were removed to make way for under-slab plumbing and ventilation pits for the new body shop.

Next week, the plumbing (trench drains and sanitary sewer lines) work begins underground rough-in operations.  After that, construction really amps up a notch as we can button up the slab and start building from the slab up.

Some exploratory rock excavation also took place out back, and with construction staking now complete, work on the rear drive will continue next week.

IMG_20160217_151704926.jpg