It’s been a busy week at the Michael Jordan Collision Center in Durham, NC.
Michael Jordan Collision 2016-04-01 from Eddie Gontram on Vimeo.
Metal stud framing is now complete on the interior, and electrical wall rough-in is also nearing completion. Plumbing rough-in finished earlier this week.
On the exterior, the new oil-sand separator tank (2,000-gallon concrete vault) was installed under the front parking lot. Given the amount of rock encountered in other areas, we were relieved this installation went fairly smoothly.
A new sidewalk and steps was formed and poured to connect the Upper Level with the main entrance at the Lower Level.
Finally, the paint booths arrived and are about 50% complete. They should be finished by the end of next week when the prep decks arrive.
This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.