Bone & Joint Surgery Clinic – Week 5

Week 5 was even busier than Week 4 at the Bone & Joint Surgery Clinic project in Raleigh, NC.  The tight schedule on this project is proving a challenge in this occupied building, but we are managing, so far.

Rough-in inspections were signed off so sheetrock installation has begun.  Sound batt insulation is installed between the metal stud framing.  Mechanical and electrical rough-in continues overhead.

The future 9,000-square feet tenant space will soon be home to the Bone & Joint Surgery Clinic.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

Wake Spine – Week 5

Things are starting to take shape at the Wake Spine project.  Sheetrock has been installed and (mostly) finished.

Mechanical and electrical rough-in continues overhead while Plumbing rough-in finishes up underneath.

The future 4,500-square feet tenant space will soon be home to the Wake Spine Clinic.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

Bone & Joint – Week 4

Week 4 has seen a flurry of activity.  A complex project with a tight schedule is keeping us hopping, but we were up to the task.

Metal stud framing, electrical and plumbing rough-ins are nearing completion.  Inspections should be signed off early next week, allowing sheetrock hanging to begin in this suite.

The future 9,000-square feet tenant space will soon be home to the Bone & Joint Surgery Clinic.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

Wake Spine – Week 4

Week 4 at the Wake Spine project has seen another week of furious activity.  A complex project with a tight schedule, over an occupied tenant space (with near 24/7 business hours) has proven challenging, but we were up to the task.

Metal stud framing, electrical and plumbing rough-ins are complete and inspected.  Sheetrock hanging has begun in this suite.

The future 4,500-square feet tenant space will soon be home to the Wake Spine Clinic.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

AECOM/URS/NC Turnpike Authority – Week 2

Construction entered the 2nd week of the expansion of the AECOM/URS call center space in Morrisville, NC.  AECOM/URS is a subcontractor for the NC Turnpike Authority and manages toll collection for the agency.

Demolition is now complete, and wall framing has begun.  Electrical rough-in, concrete removal and plumbing rough-in are all on the schedule for next week.

The expanded office space will add much needed seats in the company’s call center space as more toll roads come online in North Carolina.

The project is being delivered via the Architect-led Design-Build process with Gontram Architecture.

Construction is scheduled to be complete in early 2018.

Bone & Joint Surgery Clinic – Week 3

Metal stud framing is complete and electrical rough-ins are nearing completion.  Plumbing rough-ins are underway and mechanical work is getting started.  Sheetrock should begin being installed early next week.

The future 9,000-square feet tenant space will soon be home to the Bone & Joint Surgery Clinic.  The fitup construction will feature sound attenuating exam room walls, luxury vinyl tile, and energy-efficient LED lighting.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

Wake Spine Medical Office Fitup – 03

Wake Spine is under construction in its 3rd week. It is underway in the same building as the Bone & Joint Surgery Clinic.

Metal stud framing is complete and electrical rough-ins are nearing completion.  Plumbing rough-ins are underway and mechanical work is getting started.  Sheetrock should begin being installed early next week.

The fitup construction will feature sound attenuating exam room walls, luxury vinyl tile, and energy-efficient LED lighting.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

AECOM/URS/NC Turnpike Authority is Expanding in Morrisville

Construction started this past week on an expansion of the AECOM/URS call center space in Morrisville, NC.  AECOM/URS is a subcontractor for the NC Turnpike Authority and manages toll collection for the agency.

The expanded office space will add much needed seats in the company’s call center space as more toll roads come online in North Carolina.

Demolition work commenced this week.

The project is being delivered via the Architect-led Design-Build process with Gontram Architecture.

Construction is scheduled to be complete in early 2018.

Wake Spine – 02 – Framing in progress

In the 2nd week of construction on Wake Spine’s latest location, metal stud framing was well underway.  20-gauge metal studs line the halls and divide exam rooms.  Electrical boxes are roughed-in and plumbing work is underway.

Resilient channel is run horizontally from stud to stud to help reduce sound transmission between exam rooms.

The new Raleigh, NC location is expected to be open for patients in January 2018.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture

Bone & Joint – 02 – Framing underway

Week 2 of construction was busy with wall framing, electrical rough-in, and plumbing. Some walls were treated with resilient channel framing to reduce noise transmission between exam rooms.

 

The new Raleigh, NC location is expected to be open for patients in January 2018.