Week 5 was even busier than Week 4 at the Bone & Joint Surgery Clinic project in Raleigh, NC.  The tight schedule on this project is proving a challenge in this occupied building, but we are managing, so far.

Rough-in inspections were signed off so sheetrock installation has begun.  Sound batt insulation is installed between the metal stud framing.  Mechanical and electrical rough-in continues overhead.

The future 9,000-square feet tenant space will soon be home to the Bone & Joint Surgery Clinic.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture