Wake Spine is under construction in its 3rd week. It is underway in the same building as the Bone & Joint Surgery Clinic.

Metal stud framing is complete and electrical rough-ins are nearing completion.  Plumbing rough-ins are underway and mechanical work is getting started.  Sheetrock should begin being installed early next week.

The fitup construction will feature sound attenuating exam room walls, luxury vinyl tile, and energy-efficient LED lighting.

The project is being delivered through the Architect-led Design-Build process with Gontram Architecture