Week #8 at the North Carolina Turnpike Authority’s toll operations building showed progress. Ceiling grid installation and electrical work overhead is underway.  Prime paint is complete.  Lights will be installed next week along with HVAC diffusers.

This project is due to be complete by late January, 2018. So far, so good.

This project is being provided to the Owner via the Architect-led Design-Build process with Gontram Architecture.